Belgian authorities order Google to stop construction of data centre after inspectors found the company continued building despite permit withdrawal

News Serbia Editorial team · AI-written, reviewed under our editorial standards · · Reading time 6min read · Views 0 ·
Key — Belgian authorities ordered Google to stop construction of a data centre in the south of the country after inspectors found the company continued building despite the withdrawal of its permit.

Belgian authorities ordered Google to stop construction of a data centre in the south of the country after inspectors found the company continued building despite the withdrawal of its permit. Inspectors found that the building was nearly complete and structural work was finished, even though the permit had been rejected. A regional official stated that about 300 workers received an oral order to stop work, which was later confirmed in writing.

Illegal construction of 3-hectare building

The regional administration announced that a criminal complaint would be filed regarding the suspected illegal construction of a 3-hectare building. The data centre is located in an industrial park in Izo-Préles, about 15 kilometres west of Charleroi, on the site of a former coal mine. The complex covers about 50 hectares, and the disputed building is one of three data centres originally planned by Google for the site.

In 2024, the company obtained a permit for three smaller buildings with air cooling systems. A year later, it requested a change to combine two buildings into one larger one, switching to water cooling from the nearby Sambre river. The company plans to use up to 600 cubic metres of water per hour for cooling.

Permit withdrawal and court ruling

Regional authorities initially approved the changes in April, but the Minister of Infrastructure in August withdrew the decision after complaints and protests. Google challenged the decision before the Belgian Council of State, with a ruling expected on January 7.

Greenpeace released a report this week with aerial and satellite photos, claiming Google continued construction after the August permit withdrawal. The company argues that the original permit remains valid.

Regional officials confirm the order

Raphael Stokis, regional official for public service in Wallonia, said that inspectors found the building nearly complete and structural work finished, even though the permit was rejected. Nicolas Yernaux, spokesperson for regional authorities in Wallonia, said that the building covers 30,000 square metres.

The company has appealed the decision to the courts, and a hearing is expected in January.

Glossary

  • Charleroi — The data centre is located in an industrial park in Izo-Préles, about 15 kilometres west of Charleroi, on the site of a former coal mine.
  • Sambre river — A year later, it requested a change to combine two buildings into one larger one, switching to water cooling from the nearby Sambre river.
  • Belgian Council of State — Google challenged the decision before the Belgian Council of State, with a ruling expected on January 7.

This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact

How did you like this post?

Comments 0

Be the first to comment

Contact us

← News Serbia Home
News Serbia Get new posts by emailSubscribe to receive new content via email. Unsubscribe anytime.
Was this helpful?Share it with friends & social